Fencing will be removed and the 100 Block will be open by the end of the day Friday December 2nd 2016. This Week: Energize street lights Completion of majority of brick work Clear work site parking lot Line painting (weather permitting) Fence removal Overall cleanup Next Week: Final approvals & walk through Brick touch ups and adjustments as needed Landscaping /...

The 19th annual Royal LePage Locations West Realty Santa Claus Parade is just around the corner! Bring a chair, blanket and hot cup of cocoa to Main Street on December 3rd, 2016 and watch Penticton's festive floats make their way down to Front Street from White Avenue starting at 4:00pm. Santa will be visiting with children in the Penticton Lakeside Resort listening...

This Week: Tree planting Final asphalt paving areas Sign installation Electrical & Street Light wiring Link Rd works continued Ongoing brick work Next Week/Coming Weeks: Line painting Bollard installation Vendor Power receptacle installation Energize Street Lights Ongoing brick work Parking 13 stalls will be in front of City Hall with 2 being marked for people with accessibility needs. In total there...

Phase 2 Construction Update This Week: Pressuring testing storm drains Concrete pours including backing curb and ramps Asphalting (end of week) Brick paving stones – North East and West Wheelchair ramp installation Completions: Lamp bases Irrigation laterals Water mains Tree wells installed Next Week: Light posts installed and leveled Brick paving stones - intersection and Link Rd Electrical kiosk installation and energized ...

https://www.youtube.com/watch?v=Yj_WTGaDvWw Thanks to Castanet for coming down and covering our annual Halloween event! The rain and wind held out making for a wonderful evening of family fun with some incredibly cute (and spooky) costumes from people of all ages. Check out the full Castanet article here: http://www.castanet.net/news/Penticton/179700/Horrors-on-Front-Street

This Week: Storm drain completion Lamp base installation completion Final curb pours, mid-block ramp and backing curbs Underground Electrical completion Brick Paving South East - pedestrian access maintained at all times Next Week/Coming Weeks: Brick paving works continuing Sign base installs continued Street lights assembled and installed on pedestals – Wiring and energizing in the coming weeks Asphalt paving (weather...

This Week: Martin St water main completion Curb pour & forming including side walk pours on Link Rd Brick Paving Tree well install completion Next Week: Brick paving ongoing Vendor power pedestal installation 10Link Rd concrete pour Wheelchair access to City Hall will be maintained at all times, throughout brick works in the area. Downtown businesses are open and pedestrian access is...

Ghosts, ghouls and zombies, oh my! Halloween is upon us which means it's time for the Skaha.ca Nightmare on Frontstreet. The annual all-ages halloween costume parade starts at 4:00pm in Nanaimo Square (Nanaimo Ave and Main Street) and heads North on Main Street ending on Front Street. Be sure to show up a few minutes early to line up...