Downtown Revitalization

Downtown Revitalization

200-blk-revision-looking-north
100 Block Road Closure & Parking Map

200 Block Revitalization Updates

Fencing will be removed and the 100 Block will be open by the end of the day Friday December 2nd 2016. This Week: Energize street...

This Week: Tree planting Final asphalt paving areas Sign installation Electrical & Street Light wiring Link Rd works continued Ongoing brick work Next Week/Coming Weeks: ...

Phase 2 Construction Update This Week: Pressuring testing storm drains Concrete pours including backing curb and ramps Asphalting (end of week) Brick paving stones –...

This Week: Storm drain completion Lamp base installation completion Final curb pours, mid-block ramp and backing curbs Underground Electrical completion Brick Paving South East...

This Week: Martin St water main completion Curb pour & forming including side walk pours on Link Rd Brick Paving Tree well install completion Next...

This Week: Electrical & irrigation completion Concrete encasing electrical and irrigation Concrete curb prep and pour for Valley First Oct 5th - Oct 7th ...

Last Week: • Water service works continued including all tie ins • Installation of irrigation and storm drainage • Link road works commence Next Week & Coming Weeks: •...

  Last Week: Removals • Installed security fencing • Removals including parking meters, existing lamp standards, paver stones, sidewalks and concrete curbs • Milled asphalt • Brick salvaging This Week:...

  We will be commencing our Phase 2 of the Downtown revitalization September 6th 2016 at 7:00am in the 100 block of Main St. Grizzly will...

This Week: Brick Paving continuation & completion BMO & Starbucks Traffic signals operational Hanging floral baskets and shrubs installed Bollard installation Tree grate installation...