We will be commencing our Phase 2 of the Downtown revitalization September 6th 2016 at 7:00am in the 100 block of Main St.

Grizzly will be cutting the sidewalk to prepare for removals and fencing of the construction zone. Pedestrian access to all front doors will be maintained throughout the project, however there will be times when accessibility from one direction may be limited. When this happens there will be signage and directions given to the public on how to reach your businesses.

First steps will be the removal of street furniture, garbage cans, parking meters, street lights, asphalt and sidewalks. Grizzly will begin work on the north end of the 100 Block installing the water and storm sewer mains working south towards Westminster Avenue.

Grizzly will maintain a mid block crossing from the north side of City Hall across to the east side of the 100 Block. The crossing will not be available at certain times when they are working directly in the vicinity and the crossing will not be safe for pedestrians.

Businesses will receive hand delivered project updates and notifications on this project moving forward starting September 13, 2016.